Friday, April 23, 2021

Data-center outages: Causes are changing, report says

A new survey by the Uptime Institute found that power issues are becoming less of a problem for data center operators, but networking and software issues are emerging as an increasingly bigger problem.

The Uptime Institute's third Annual Outage Analysis notes that while improvements have been made with technology and availability, outages remain a major industry, customer, and regulatory concern. 

The report also shows that the overall impact and direct and indirect cost of outages continue to grow. When asked about their most recent significant outage, more than half of respondents reported an outage in the past three years and estimated its cost at more than $100,000; among those respondents, almost one-third reported costs of $1 million or above.

To read this article in full, please click here


Thanks to Andy Patrizio (see source)

No comments:

Post a Comment